The Mon-Oakland Mobility Project will be developed in two phases. Phase 1 will begin in Summer 2019 and focus on the Junction Hollow and Four Mile Run segments of the project area. Phase 2 will focus on the Sylvan Avenue segment of the corridor and begin in Fall 2019.

2019 2020 2021
SpringSummerFall WinterSpringSummer FallWinterSpring
Public
Involvement
    • Stakeholder Meeting
    • Public Meeting w/PWSA
    • Email Update
    • Website Update Live
    • Public meeting
    • Email Update
    • Stakeholder Meeting
    • Website Update
    • Public meeting
    • Stakeholder Meeting
    • Resident Advisory Group Meeting
    • Website Update
    • Email Update
    • Stakeholder Meeting
    • Website Update
    • Stakeholder Meeting
    • Resident Advisory Group Meeting
    • Website Update
    • Email Update
Junction Hollow & The Run Segments
    • Geotechnical Investigation
    • Preliminary Design
    • Lidar Survey & Mapping Development
  • Final Bid Package

    • Final Design
Sylvan Segment
    • Geotechnical Investigation
    • Lidar Survey & Mapping Development
    • Preliminary Design
  • Final Bid Package

    • Final Design
Contact Us

For more information, please contact: mon‑oaklandmobility@pittsburghpa.gov

City of Pittsburgh Department of Mobility & Infrastructure

Room 301 City-County Building
414 Grant Street
Pittsburgh, PA 15219

Connect with Us